Project Facts at a Glance:
- Site establishment under Genco completed in 18 months (Oct 2010 to March 2012)
- Project site establishment (Stage #1) prior to EGM / Balance of Plant contractor
- Genco scope included: Site Civil & Earthworks / Fencing / 3500m2 Admin & Workshop Construction / 5.3km HV Interconnect / power Transformers / HV Switchroom / Gas Connection
- Genco scope included full Regulatory / Environmental & Heritage compliances
- Genco managing up to 50x site crew and contractors
- Project Cost USD $75 Million
Of Significance (prior to March 2012 handover):
- A State Government project reporting through the client to the Minister of Energy
- A "flagship" facility passing intense heritage, environmental and public scrutiny
- 5.3km 11kV UG Interconnect cables installed through a town, with nil disruption to existing underground services
- Project handed over to EGM / BOP contractor, independent project audit confirmed project status as "on budget, to schedule" for completion December 2012
- Project handed over with independent HSSE and Quality Assurance Audits confirming 100% compliance
Project photo Gallery - During construction
Click top left image to start scrolling through
Project photo Gallery - Genco works completion and handover (March 2012)
Click top left image to start scrolling through
- Project handover to EGM / BOP contractor. Independent project audit confirming project status as "on budget, to schedule" for completion Dec 2012
- Project handed over with independent HSSE and Quality Assurance Audits confirming 100% compliance
- Client undertook a local community and media site tour, publicly ratifying site and project status