21MW Solar Titan 250 

Gas Turbine Power Plant


Project Facts at a Glance: 

  • Solar Titan 250 Closed Cycle Gas Turbine Powerplant
  • with 80 Ton Heat Recovery steam generator   
  • Total Project, Construction & Compliance Management
  • Managed up to 150x site crew and contractors  
  • Project cost USD $50 Million
  •  

Of Significance:

  • Construction including pre-commissioning completed in just 8 months
  • Successful construction of the facility in the middle of a live, fully operating Petro Chemical refinery - very rigorous & intense daily Work permitting and Safety compliance, whilst meeting critical schedule requirements.
  • Included seperate 2.5km, 22kV underground and overhead Interconnection via 2x live substations details here
  • Genco scope included securing full Regulatory Compliance sign off (gas / electrical / mechanical / building)

Project photo Gallery
Click top left image to start scrolling through

  • A bare site start, Boiler equipment being delivered to site
  • Site prepared for Gas Train build
  • Gas Turbine power plant delivered to site
  • Generator delivery
  • Generator heavy lift and placement
  • Exhaust stack heavy lift
  • Exhaust stack heavy lift
  • Ready to commence heavy lift of GT Air Intake structure
  • Heavy lift and placement of Air intake
  • GT package assembled, air intake erected
  • Structural steel furniture being erected
  • 3x underground feeders connecting Generator output
  • Main HV feeder cables entering HV Switchroom
  • The start of 2.3km HV underground interconnection - Connecting power plant to the industrial consumer
  • 8 months later - Solar Titan 250 GT Power plant & Steam boiler - Complete & preparing for load reliability testing
  • 8 months later - Solar Titan 250 GT Power plant package - Complete & preparing for load reliability testing
  • 8 months later - Completed high voltage Switch room
  • 8 months later - Solar Titan 250 GT Power plant & Steam boiler - Complete & preparing for load reliability testing