Project Facts at a Glance:
- 1600 Ton Coal Dredger in open cut coal mine pit
- Fire damage shutdown 30% disassembly and re-fabrication of major Structural Steelworks
- Total Mechanical disassembly and service
- Total HV / LV Electrical refit
- Fire suppression and Detection design and installation
- Genco managing 70x site crew and Contractors
- Completion 5x months
- Project Cost USD $8 Million
Of Significance:
- Project was managed from being handed a fire damaged wreck through to commissioning and handover
- Schedule required running crew on 24 / 7 shifts
- Project required full safety compliance operating within a fully operating open Coal Mine pit.